This document is to outline the general building process and time line from lot selection to moving in your new home. The total process has many more steps, but this is to give the customer a very general overview of the process.
1Select Lot (Time Frame: 1 Month)
Survey
Soil test
Details on golf / social membership fees
Purchase lot
2Select House Plan (Time Frame: 2-4 Months)
Sized to fit selected lot
Garage location (front or side loading garage)
Square footage for your budget and lifestyle
Best design to fit your lifestyle (etc. master on first floor, bonus room, office)
Can the selected house fit on lot with driveway and setbacks
Design house and driveway/porches/patio for max. impervious
Define pool and spa area
Preliminary site plan from surveyor with house and all impervious area on map
3Write Contract For Selected house (Time Frame: 1 Month)
Select plan for your budget
Define all exterior materials and colors
Select windows and doors
Select exterior driveway and walkway materials and colors
Select roofing materials and colors
Define room by room design and built details
Finalize pricing and sign contract
Select building start date
4Complete POA/ARB Package (Time Frame: 1 Month)
Define all exterior materials and colors
Select windows and doors
Select exterior driveway and walkway materials and colors
Select roofing materials and colors
Finalize all selections
Sign final application
Submit two site plans, two house plans, and selection package
Sign plans and site plans
Write checks for application and bond fees
Pay water meter fee/ acreage fee/ irrigation fee (Brunswick County)
Builder applies for building permit
5Start Construction (Time Frame: 6-9 Months)
Pay builder's construction deposit
Construction begins
Make item selections within allowed budget and timeline
Complete propane application and pay fee
Finalize landscaping plan and submit to POA/ARC
Inspect construction progress at least 3 times during the building phase
Pay construction draws according to draw schedule
Do final walk thru with builder to write punch list for repairs
Inspect repairs
Pay for final change orders
Move in
6Post Construction (Time Frame: 1 Month)
Receive certificate of occupancy
Receive as built survey
Receive termite bond
Receive house keys
Receive elevation certificate (if required) (in floodplain)
Write 30 day punch list
One year punch list and final review